|
|
November 26, 2007
From DOT: SUMMARY
-
Traffic congestion levels along
Olympic and Pico Boulevards justify the implementation
of all available traditional measures and consideration
of non-traditional operational measures.
-
Supervisor Yaroslavsky’s proposal
was evaluated by the Department of Transportation (DOT)
and elements of the proposal were found not to be
feasible.
-
DOT has evaluated other alternative
measures and has determined that the three measures of
(1) the addition of peak period lanes; (2) directional
signal operation; and (3) preferential directional flow
are feasible.
-
The addition of peak period lanes
for both the AM and PM peak periods will have initial
adverse impacts to parking availability until schools,
religious institutions, businesses, and customers can
adjust to the new parking restrictions, as has occurred
elsewhere in the City.
-
Directional signal operation and
preferential directional flow would improve traffic flow
for traffic traveling westbound on Olympic Boulevard and
eastbound on Pico Boulevard, but would degrade traffic
flow for traffic traveling eastbound on Olympic
Boulevard and westbound on Pico Boulevard.
However, the overall benefit is that motorists
would have travel choices for improved directional flow
that are not achievable through conventional measures.
-
Each of the three feasible measures
hold the potential of incrementally reducing commuter
traffic on neighborhood streets along the Olympic/Pico
Corridor due to improvements in traffic flow on the
arterial routes.
Further, access to and traffic volumes on Motor
Avenue and Overland Avenue (northerly of Pico Boulevard)
would be incrementally reduced due to metered left turn
phasing to those routes.
-
A three-phase approach (first peak
period lanes, followed by directional signal operation,
followed by preferential directional flow operation)
would allow the impacts of each phase to be assessed
before advancing to the next phase.
-
The cost to implement the first
phase is estimated to be $300,000, which can be entirely
financed from the Special Parking Revenue Fund.
The cost to implement the second phase is
estimated to be $300,000, which can be financed from a
combination of the West Los Angeles Improvement and
Mitigation Specific Plan Fund and the ATSAC Trust Fund.
The cost to implement the third phase is
estimated to be $1,500,000, which could be financed from
the West Los Angeles Improvement and Mitigation Specific
Plan Fund and other funds to be designated.
-
At this time, funding is requested only for Phases One
and Two.
Phase 1:
AM and PM Peak Period Lanes on
Olympic/Pico Boulevards
Peak period lanes provide added
capacity during peak periods by utilizing the area reserved
for curbside parking as travel lanes.
Typically, major arterials have
continuous peak period lanes to provide a consistent or
maximum number of travel lanes.
An inconsistency in peak period
lanes limits roadway capacity in critical segments by not
allowing continuous travel lanes, creating traffic merging
conditions and increasing the potential of rear-end and side
swipe accidents.
The primary drawback of the
installation of peak period lanes is the loss of on-street
parking during the peak periods.
The objective of this alternative is to
achieve continuous peak period curb lanes in each direction
during both the AM and PM peak periods by implementing
uniform peak period parking restrictions on Olympic and Pico
Boulevards within the study segment.
Along the study segments of
Olympic Boulevard between Centinela Avenue and La Brea
Avenue, and Pico Boulevard between Centinela Avenue and San
Vicente Boulevard, there are significant distances where
peak period lanes are already in place.
However, there are sections
where either an AM peak period restriction, PM peak period
restriction, or both are not present.
In addition, in some sections
the hours are not consistent from block to block.
This concept will require the
addition of peak period lanes and parking restrictions in
the missing sections and consistent hours along the streets.
This
phase is expected to improve overall travel speeds by 2 mph
in those sections where peak period lanes and parking
restrictions do not exist.
The
cost for Phase 1 is approximately $300,000 and can be
financed from the Special Parking Revenue Fund.
Phase 2:
Directional Signal Operation
Among the many benefits of one-way
streets are increased travel speeds and reduced delay
accomplished in part by improved traffic signal timing.
However, a one-way pair
operation of Olympic and Pico Boulevards is not feasible
because of the distance of separation between the two
streets (¼ to ½ mile).
Instead, DOT has developed a
strategy to treat these two-way streets as a pair and time
the signals to favor one direction of travel over the other.
This strategy is termed
“directional signal operation”.
According to this strategy,
Olympic Boulevard would favor westbound travel and Pico
Boulevard would favor eastbound travel.
This phase is expected to improve
travel speeds by 6 mph (from 17 to 23 mph) in the
preferential directions, with a small degradation of 1 mph
(16 to 15 mph) in the opposite directions.
Although the preferential
direction benefits and the minor direction degrades, the
overall benefit is that motorists have a choice and a
smooth-flow option not otherwise available through
conventional measures.
The cost for Phase 2 is approximately
$300,000.
The portion westerly of Beverwil
Drive would cost approximately $150,000 and is eligible for
financing from the West Los Angeles Improvement and
Mitigation Specific Plan Funds.
The remainder can be financed
from the ATSAC Trust Fund.
Phase 3:
Preferential Directional Flow
Operation
DOT has developed a strategy to operate
two-way streets in an alternative way – with preferential
flow in a given direction.
Under this concept, Olympic
Boulevard would provide preferential treatment for westbound
through traffic and local access only for eastbound traffic.
Likewise, Pico Boulevard would provide preferential
treatment for eastbound through traffic and local access
only for westbound traffic.
This operational concept is
termed “preferential directional flow”.
It is feasible between Centinela
Avenue and a point east of La Brea Avenue.
It has been tried on a much
smaller scale along Figueroa Street between Olympic and
Exposition Boulevards and along Hill Street between 1st
and 12th Streets.
There is no known similar operation of two paired streets
separated by such a great distance (¼ to ½ mile), of which
DOT staff is aware, anywhere in the nation.
Simply stated, preferential directional flow would have the
peak period lane plus the adjacent lane to provide transit
service and local access for the “minor” move.
All other lanes would serve the opposing preferential
flow. Phase 3
complements the
Phase 2, directional signal operation, which would tend to
attract more motorists to the street and direction that
offers improved directional flow.
As motorists gravitate to the preferred direction and
traffic volume increases, it is possible that the travel
times and speeds might decrease.
Therefore, the implementation of this alternative
would be necessary to accommodate the increase in traffic
volume in the preferred direction and maintain the initial
benefit of Alternative 4 (+6 mph in the preferred
direction).
The cost for Phase 3 is approximately
$1,500,000 and is eligible for financing from the West Los
Angeles Improvement and Mitigation Specific Plan Fund and
other funds to be designated.
Final funding will be identified
when a decision is made to move forward to Phase 3.
Figure
2:
Directional Signal Operation

Figure 3:
Preferential Directional Flow Operation
|